Pinetree Progress Reports

National Archives of Canada


Pinetree Progress Reports
Report No. 14
Dated 15 September 1953

Page 1 of 8

Equipment Availability Schedule

This table originally detailed equipment deliveries in the Progress Report as a guide for installation planning but shipments have reached such a stage of completion that it will not be reproduced in this or future issues.

Microwave Communications for NEAC Sites – (Southern portion – Goose Bay to Gander)

A list of proposed microwave sites for the Goose Bay – Gander portion of the system, selected by aerial survey and checked by ground survey is noted below:

Station No. Location Type
100 Gander (N-25) Terminal
101 Embree Repeater
101A Fleury Bay Repeater
102 Snooks Arm Repeater
103 Ste. Barbe Repeater
104 Belle Island Repeater
105 St. Julien Repeater
106 St. Anthony (N-26) Terminal
107 Quirpon Repeater
107A Belle Isle Repeater
108 Cape St. Charles Repeater
109 Ship Harbor Repeater
110 Stony Island Repeater
111 Domino Harbor Repeater
112 Gready Island Repeater
113 Cartwright (N-27) Terminal
114 Tug Harbor Repeater
115 Rigolet Repeater
116 Reed Point Repeater
117 Long Point Repeater
118 North West River Repeater
119 Goose Bay (N-24) Terminal

Proposals on microwave equipment submitted by selected Canadian manufacturers have been received by the Department of Defence Production and Pinetree Project Office and are now being considered by the prime contractor (Bell Telephone Co. of Canada).

Contracts for the production of microwave equipment are imminent but completion of the installations cannot be expected before late 1955.

Newfoundland Tail Cables

Shipments of material for tail cable construction have reached Port au Basque, Nfld. And Sydney, N. S. Supervisors are already on the job and property assessments are being negotiated. Staking of the re-building job at Harmon is underway. Completion of work is scheduled for Dec 53.

Page 2 of 8

Installation

(i) – RCAF Program

As noted in previous reports limited operations are now being conducted at the following RCAF sites: Lac St. Denis, Mont Apica, Foymount, Edgar, Parent, Senneterre, and Falconbridge. Installation work is proceeding satisfactorily at Chatham. Delays are still being encountered in getting work started at Holberg, for which the installation contract is not yet approved. Activation of Comox and Tofino is dependent upon the delivery of the radar equipment, delivery of which is not expected before early 1954.

Microwave circuits between St. Hubert, Lac St. Denis, Mont Apica, Foymount and Edgar are now complete. Some VHF circuits are in operation at all sites. HF circuits between Mont Apica, Lac St. Denis, Foymount and Edgar will be completed by 15 Oct 53.

The limited operation date for Chatham has been changed to Sep 53 from Dec 53.

(ii) – Radar Extension Plan – Interior of Canada

Ramore – AN/FPS-3 main radar installation is completed (less radomes and pressurizing equipment) and is accepted and operating. Outside telephone plant is completed and accepted. Inside plant is completed and being tested. Antenna farms are 98% complete. Pressurizing and IFF equipment to be completed during Oct 53.

Pagwa – AN/FPS-3 main radar is completed, accepted and operating (less radomes and pressurizing equipment). Progress on other facilities essentially the same as for Ramore.

Beausejour – AN/FPS-3 main radar is completed, including radomes and pressurizing equipment. IFF equipment is installed and tested. Completion of communications facilities is being held up pending construction of the outside plant which is scheduled for the immediate future.

Puntzi Mountain – AN/FPS-3 main radar is completed (less radomes and pressurizing equipment) and ready for acceptance. Work on communications facilities is now in progress.

Sydney – AN/FPS-3 radar installation is completed and undergoing flight tests.

Installation has started at Clarke City (Moisie), Halifax and Ste. Marie. It is expected that limited operation dates will be met. The limited operation date for Halifax has been changed from 27 Feb 54 to Mar 54 and that of Clarke City (Moisie) from 1 Oct 53 to Nov 53. Installation work is also in full progress at Armstrong, Sioux Lookout, Baldy Hughes and Saskatoon Mountain.

(iii) – Radar Extension Plan – NEAC Area

Installation work is under way at Goose Bay, Gander, St. Anthony, Cartwright, Hopedale, Saglek and Frobisher. With the exception of Goose Bay (an AN/CPS-6B site) it is expected that the primary radar facilities (AN/FPS-3 sets) will be completed within the next sixty days. Adjunct communications facilities will also become available for acceptance at approximately the same time.

Completion of AN/CPS-6B main radar facilities at St. John’s, Stephenville and Goose Bay will be delayed until early 1954 because of production difficulties.

Page 3 of 8 is missing.

Page 4 of 8

Construction – Percentage of Completion – Sites N-25 to N-31 incl. – 15 Sep 53

Matrix showing percentage of completion.

Page 5 of 8

PINETREE PROJECT – RADAR EXTENSION PLAN – MAJOR EQUIPMENT AVAILABILITY – 15 Sep 53

Matrix showing status of equipment.

Page 6 of 8

PINETREE PROJECT – RADAR EXTENSION PLAN – MAJOR EQUIPMENT AVAILABILITY – 15 Sep 53

Matrix showing status of equipment.

Page 7 of 8

PINETREE PROJECT – RADAR EXTENSION PLAN – MAJOR EQUIPMENT AVAILABILITY – 15 Sep 53

Matrix showing status of equipment.

Page 8 of 8 is missing.